Campus Expansion

Click on the artistic rendering below to see the finalized building plans.

Keep scrolling down for more information.

The Latest Building Project News

  • Most of the structural masonry work is now complete. The remainder of the walls will be made from steel framing.
  • The delivery of steel to fabricators is set for next week. The fabricators will be cutting everything to size before delivery to St. John's, which will make for a speedier construction once the steel is on site.
  • The construction company has changed the sequence of things to make things a little easier on the timeline. The next major phase will be putting up the steel framing, followed by the 2nd floor deck and slab pour. The downstairs slab will be poured in early March, and after that, the rest of the project should move quickly.
  • The design team will be visiting the St. John's Welcome Center in the next week to finalize materials for the new building that will match the design of the Welcome Center.
  • Occupancy permits are still expected early May.


Please leave the close parking (adjacent to the Welcome Center and along 68th St.) for those members who cannot walk longer distances. Thanks!